How To Create S Curve In Microsoft Project 2016
Ms Project is a powerful project management tool to plan, monitor, control, analyse and forecast project's status, progress and performance.
Ms Project has Earned Value Analysis that allows us to plot S-Curve chart displaying cumulative cost, labour hours or other quantities plotted against project's time span. But I came across a question asked by my student, i.e. how to display S-Curve chart with percentage complete against the time, side by side comparing the progress between your baseline and actual completion.
In this tutorial we will show walk you through how to create a chart to display the percentage completion of Baseline Cumulative Work and Cumulative Actual Work against the time.
Here is the step:
1. In Ms Project, select Report > Visual Reports > Baseline Work Report.
2. Click Edit Template button.
3. At the Field Picker dialog box, select field Baseline Cumulative Work, click Add
4. At the Field Picker dialog box, select field Cumulative Actual Work, click Add.
5. Then click Edit Template.
6. The Visual Report is generated and opened in Excel Program. Select Assignment Usage worksheet.
7. In Excel Program, change the PivotTable fields to as image below.
8. Expand the Year, Quarter and Week fields. You may filter and modify the data as you want.
9. For our case, we will:
- Hide the Quarter column: right click anywhere at Year/Quarter/Week column, choose Show/Hide Fields > untick Quarter
- Hide the value for Year 2019
10. Your PivotTable will display as shown below.
Now, we want to duplicate the table and change the values to percentage. Then do the following:
11. Copy the table and Paste As Value to the empty column on the right.
- Delete the date for each week.
- Change the Cumulative Actual Works Grand total to 5220
12. Select cell in the first row of each column and enter the following formula.
For Cell I5:=C5/$I$23
For Cell J5:=D5/$J$23
For Cell K5:=E5/$K$23
13. Copy down the formula, and format the value to percentage style.
14. Highlight the data and create a Line chart.
15. Let's modify the axis to change the maximum value to 100%.
Right click at the vertical axis, choose Format Axis.
16. In Axis Options, change maximum value to 1.
17. The chart has now showing Percentage work completed for Baseline, Actual, Planning against the time.
Here are the sample files to download: Ms Project Sample, Excel Report Sample
By Chee SK | LinkedIn
Cempaka Technology Sdn Bhd
Pusat Latihan Komputer Cempaka
~Your HRDC Premiere Training Provider~
Unit 6, Level 4, SetiaWalk Mall (Block K), SetiaWalk, Persiaran Wawasan, Pusat Bandar Puchong, 47160 Puchong, Selangor, Malaysia.
Tel: 603-80684461, Fax: 603-80684240
1-28, Jalan PM4, Plaza Mahkota, 75000 Melaka, Malaysia
Tel: 606-2835955, Fax: 606-2845955
How To Create S Curve In Microsoft Project 2016
Source: https://www.cemtech.biz/project-tutorial-baseline-actual-completed-s-curve-chart